占位边距
Leveraging our core product strengths,we offer three key solutions to global clients:First,Smart Grid Optimization Solutions,which utilize recloser controllers and distribution automation systems to enable rapid fault location and automatic restoration, enhancing power supply reliability. Second, Industrial/Residential Energy Storage Solutions, tailored to diverse load demands, helping clients achieve peak shaving,backup power assurance,and energy cost control.Third,EV Charging Network Solutions,providing AC/DC charger selection, network design, and O&M services, compatible with regional standards like North America's NACS and Europe's CCS2. These solutions have been successfully deployed in factories,office buildings,residential communities,and public transport,effectively addressing customer pain points in energy utilization,power stability,and charging convenience.

Prefabricated Boost Transformer Substation Solution for Photovoltaic Power Plants in Skid-Mounted Design


The Rockwell Energy modular prefabricated step-up substation integrates medium-voltage switchgear, step-up transformers, and low-voltage distribution into a steel frame that has been factory-assembled and undergone routine testing.

Upon arrival at the site, it can be “put into operation immediately”—shortening the grid connection cycle from the 3–6 months typically required for conventional substations built on-site to about 2 weeks. The amount of civil construction is reduced by 70%, and the open-air natural air-cooling system allows the transformer to operate at full capacity without derating.

Prefabricated Boost Transformer Substation Solution for Photovoltaic Power Plants in Skid-Mounted Design

1. Why do photovoltaic projects lose revenue at the step-up substation stage?

  • Mismatch in construction schedules: While components and inverters can be installed within a few weeks, the 35kV civil engineering and step-up substation takes 3 to 6 months, making it the sole critical path for grid connection.
  • Remote sites: weak construction capabilities, numerous concurrent operations, and uncontrollable on-site installation quality.
  • Phased expansion: Each phase repeats the civil engineering cycle, making capacity expansion uneconomical.
  • On-site operations and maintenance are challenging: power stations are scattered, and there’s a shortage of maintenance personnel.

Taking a 100 MW power plant as an example, each month of delay results in a loss of approximately 1% of annual power generation (this is a rough estimate; the actual figure will depend on project-specific calculations).

II. Standard Product Platform (Committed Values, Not “Examples”)

Parameter

Rockwell Energy skid-mounted platform

Standard anchor point

Rated voltage

Medium voltage: 12/24/35/40.5 kV; Low voltage: 400–800 V

IEC 62271-200

Transformer capacity

Oil-immersed, standard series 0.63–7.5 MVA

IEC 60076

Short-circuit level

25kA–3s (standard version), peak 63kA

IEC 62271-100

Protection level

IP43 / IP54

IEC 60529

Cooling method

Open-style natural air cooling, no capacity reduction.

IEC 60076-2

Operating temperature

-25℃ ~ +55℃ (heating belt option)

IEC 60068

The capacity is selected according to the standard series during the engineering design phase; the platform value will be delivered as promised.

III. Traditional Civil Construction vs. Rockwell Energy Skid-Mounted Systems (Quantitative Comparison)

Comparison item

Traditional civil-engineering substation

Rockwell Energy Skid-Mounted Substation

Power-on cycle

3–6 months

Approximately 2 weeks (subbase + lifting + wiring)

Civil engineering volume

Concrete buildings, foundations, and fences

Concrete leveling layer only

Occupying land

Large, requires an independent plot of land

Compact single-frame

Field test

Large volume, affected by weather

Factory routine testing + on-site joint commissioning

Expand capacity

One round of civil engineering per issue

Adding one skid-mounted unit is all it takes to replicate.

Migration

Not feasible

Lifting and relocation possible

Prefabricated Boost Transformer Substation Solution for Photovoltaic Power Plants in Skid-Mounted Design

4. Engineering Configuration and Grid-Connection Support

  • Primary System: Incoming line (ring main/switchgear cabinet, SF6-insulated) → Step-up transformer (oil-immersed) → Low-voltage distribution (400–800V, multiple configurations including circuit breakers/fuse disconnect switches), supporting either string inverter combiner or direct connection to centralized inverters;
  • Grid-connection protection and setting value services: Transformer protection, feeder overcurrent protection, and grid-connection protection are configured according to IEC 60255. A set of factory-delivered setting value sheets is provided, and communication interfaces with the substation control AGC/AVC (IEC 61850 / Modbus) are reserved to meet the grid’s requirements for active and reactive power regulation.
  • Reactive power support (optional): SVG or capacitor banks can be integrated according to the requirements of the connection point, and the compensation capacity shall be verified based on the PCC voltage requirements.
  • Environmental support: shade canopy, temperature control, fire alarm linkage, and full-site monitoring.

V. Acceptance Criteria (Verifiable, Anchored to Standard Clauses)

Project

Acceptance value

Standard anchor point

Grid-connected harmonics

35kV grid connection point THDu ≤ 3%

GB/T 14549-1993 Table 2 / IEEE 519-2022

Transformer temperature rise

Top oil ≤ 60K, winding ≤ 65K (ONAN)

IEC 60076-2 Table 1

Capacitor discharge (as configured)

After power failure, the residual voltage within 5 minutes ≤ 50V.

GB/T 50227-2017

Protection level

IP43 / IP54 Measured and Verified

IEC 60529

Six: Why Choose Rockwell Energy?

  • Routine factory tests for each skid-mounted unit: Complete test list provided, with report delivered along with the goods.
  • One-stop grid connection protection: Setting value adjustment, testing, and AGC/AVC interface integration are all handled by a single provider, reducing conflicts and disputes among multiple vendors.
  • Regional Delivery Records: Available for customer reference in the African, Southeast Asian, and Mongolian markets.
  • Digital Operations and Maintenance: Remote monitoring via IEC 61850 / Modbus, with alarm integration into the power plant SCADA system.

Deployed Equipment

  • Mobile Container Prefabricated Substation E-House 10kV 20kV 35kV
    OverviewThe prefabricated cabin substation is composed of a prefabricated cabin, primary and secondary substation equipment, and cabin auxiliary facilities. Prefabricated in the factory, including assembly, wiring, commissioning, etc., is transported to the construction site as a whole and installed on the foundation. It is based on the core concept of "standard distribution type" of the State Grid, and is designed on the basis of the traditional box transformer and combined with the style of th

Reference Projects

  • Angola Dadi Energy Storage 35 kV Power Quality Improvement success story
    The Angola Dadi Energy Storage power quality improvement project is a 35 kV power quality retrofit implemented on an existing energy storage plant. On-site nonlinear, high-harmonic loads such as inverters — power conversion systems (PCS) — are densely concentrated, a typical harmonic-source-intensive scenario in which harmonic pollution seriously hampers production efficiency and product quality.An H5+H7 filter compensation bank with a total capacity of 7500 kvar was provided to deliver harmonic
  • Jiangsu Suqian Rongxin Metal Products Power Quality Improvement Project-A success story in medium-frequency furnace harmonic mitigation and power quality improvement
    The Jiangsu Suqian Rongxin Metal Products power quality improvement project is a dedicated retrofit addressing the severe harmonic pollution caused by the concentrated connection of nonlinear loads such as medium-frequency furnaces in the metal products industry. An H5+H7+H11 filter compensation bank with a total capacity of 17550 kvar was installed to deliver harmonic mitigation and reactive power compensation in one.Since commissioning, the dominant 5th, 7th and 11th characteristic harmonics h
  • Mongolia South Gobi Coal Washing Plant 35 kV Power Quality Success Story
    The 35 kV power quality improvement project at a coal washing plant in South Gobi Province, Mongolia, is a dedicated retrofit addressing the severe harmonic pollution caused by the concentrated connection of variable-frequency-drive (VFD) equipment in the coal washing industry. A 5000 kvar H5 filter compensation bank was installed to deliver harmonic mitigation and reactive power compensation in one.Since commissioning, the dominant 5th harmonic has been effectively filtered, harmonic distortion
Leave your contact information to receive the full technical documentation and a free consultation from our engineers. Get the Solution Guide
Recent Solutions
Send inquiry
+86
Click to upload file
Download
Experts Electrical is dedicated to serving the personnel in the global power industry.
Join Experts Electrical, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!
App Store
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.
Email
E-mail
Chat
Manager
WhatsApp
WhatsApp