The collection features typical success cases of the company across multiple regions and industries worldwide, covering three core business areas: including a commercial and industrial energy storage system project at a factory in Europe (achieving a 30% reduction in electricity costs), an EV charging network project for a community in North America (compatible with the NACS standard, meeting the charging needs of 500+ parking spaces), and a smart grid optimization project in a region of Asia-Pacific (reducing fault recovery time by 80% through recloser controllers and distribution automation systems), among others.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study


Facing the frequency fluctuation and grid connection challenges of Colombia’s low-inertia photovoltaic power grid, this solution leverages customized recloser control and optimized frequency protection technologies to precisely adapt to the local 60Hz grid standard. It effectively addresses grid fluctuation issues under complex grid connection conditions, delivering a highly reliable and strong anti-interference grid protection solution for photovoltaic power plants and ensuring their stable and efficient power generation.

01 Project Background

1.1 Project Background

Colombia is a core market for photovoltaic (PV) development in Latin America. However, its grid environment differs significantly from others. Solar irradiance fluctuations lead to highly stochastic PV output, resulting in low-inertia grid characteristics. Additionally, strong local electromagnetic interference and frequent frequency fluctuations pose extreme challenges for fault recovery and frequency stability control.

In the initial stages of a large-scale PV plant's connection, the existing recloser controllers were not adapted to the Colombian grid. Specifically, the core 81R frequency protection failed to meet local regulation requirements. Instead of identifying faults and optimizing reclosing sequences, it exacerbated frequency fluctuations, leading to frequent tripping on the PV side. This severely impacted generation efficiency and grid stability, causing significant financial losses and O&M pressure for the owner.

To resolve these challenges, the PV plant officially introduced RW Energy 35 kV recloser controllers in 2024. Leveraging RW Energy’s technical expertise in PV grid-tied protection and frequency stability control, a customized solution was provided to precisely adapt to the local 60 Hz grid, achieving rapid fault recovery and coordinated frequency regulation.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

1.2 Core Product and Parameters

A total of 88 units of 35 kV recloser controllers, along with accessories and spare parts, were deployed.

Item

Technical Details

Product Name

35 kV PV Grid-tied Recloser Controller

Model

RWK-352HBV

Rated System Voltage

35 kV

Rated Frequency

60 Hz (Adapted to Colombia Grid Standard)

Core Functions

81R ROCOF Protection, Adaptive Reclosing, Fault Identification

Supply Quantity

88 Units

Installation Site

Grid-tied side of Colombia PV Plant

Commissioning Year

2024

1.3 Technical Drawings

The project utilized comprehensive electrical schematics for the RWK-352HBV 35 kV outdoor permanent magnet recloser controller. These drawings cover primary circuits, secondary control, 81R frequency protection logic, power supply, and communication interfaces including IEC 101/104, MODBUS, and RS485. The design precisely matches the 60 Hz frequency and 35 kV voltage requirements of the Colombian grid. Detailed wiring and control logic for permanent magnet actuators, CT/VTs, and remote control interfaces ensure stable operation under intense solar fluctuations and electromagnetic interference.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

02 Technical Design and Quality Assurance

2.1 Core Technical Design

The RWK-352HBV recloser controller is tailored for low-inertia PV grid integration, with deep optimization of the 81R function:

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

  • Algorithm Upgrade: Equipped with specialized frequency-slip locking and adaptive reclosing algorithms. It accurately identifies fault types and optimizes reclosing sequences to solve frequency fluctuations at the source.
  • Adaptive Parameter Optimization: Supports a full cycle of "Parameter Rectification - Function Debugging - Scenario Testing - Optimization Iteration" to adapt to complex Colombian grid conditions.
  • EMI/EMC Design: Utilizes high-strength electromagnetic shielding and anti-interference circuits to ensure stability under strong local interference.
  • Integrated Architecture: Integrates fault detection, protection control, and reclosing execution, simplifying field installation and O&M.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

2.2 Quality Certification

RW Energy is certified under ISO 9001, ISO 14001, and ISO 45001. All products have passed professional testing by international authoritative agencies, complying with IEC 60255 and other international protection standards.

03 Factory and Field Testing

All equipment underwent comprehensive factory acceptance tests (FAT) and field commissioning according to IEC standards and Colombian grid technical specifications:

  • 81R Frequency Protection Test: Simulated Colombian grid fluctuations to verify frequency-slip locking accuracy. Verified via multi-round slope and pulse frequency tests, achieving a 100 % accuracy rate for 81R actions.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

  • Fault Recovery and Reclosing Sequence: Simulated short-circuits and grounding faults. Fault identification response time was ≤ 20 ms, with reclosing sequences perfectly matching grid requirements.
  • EMC/EMI Testing: Simulated strong electromagnetic interference environments. Performance complied with IEC 61000 international standards with zero protection malfunctions.
  • Dielectric and Reliability Tests: Completed 1 min power frequency withstand and impulse withstand tests with zero breakdown. Performed 72-hour continuous load operation with zero parameter drift.
  • Field Commissioning: Technical teams performed multi-round parameter debugging on-site in Colombia, ensuring 100 % adaptation to the owner's and the local utility's requirements.

04 Packaging and Shipping

Equipment utilized heavy-duty export-grade moisture-proof and vibration-proof packaging. Core electronic boards were vacuum-sealed. Reinforced wooden crates were customized to withstand long-distance maritime and inland transport in Colombia. All components were clearly labeled in English and Chinese.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

05 Installation and Operation Summary

5.1 Installation Implementation

RW Energy dispatched a professional technical team to the Colombian site to provide full-process technical services:

  • Guided foundation construction, control box wiring, and grounding system installation.
  • Performed insulation tests and wiring verification for 88 units.
  • Conducted on-site energized commissioning and customized 81R parameter configuration.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

  • Final Acceptance: Successfully completed multiple rounds of on-site condition testing and optimization iterations, resolving parameter adaptation issues inherited from previous controllers and passing the final acceptance from both the project owner and the local utility.
  • Training and Documentation: Conducted comprehensive operation and troubleshooting training for local O&M personnel and handed over a complete set of O&M manuals, technical drawings, and standard operating procedures (SOPs).

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

5.2 Operation Feedback

Since commissioning, the equipment has operated stably with zero downtime, exceeding the owner's expectations:

  • Resolved Frequency Stability: The precise application of the 81R function suppressed frequency fluctuations and eliminated frequent tripping.
  • Enhanced Fault Recovery: Fault recovery time was reduced by over 80 %, significantly minimizing generation loss.
  • Improved Grid Stability: Grid-tied voltage and frequency now fully comply with Colombian national standards, receiving high praise from both the utility and the owner.
  • Reduced O&M Costs: Stable operation reduced the need for site inspections and minimized downtime losses.

RW Energy Colombia PV Plant 35 kV Recloser Controller Project Case Study

06 Full Lifecycle O&M Managed Services

RW Energy provides integrated full-lifecycle O&M services for the Colombia project, covering selection, installation, monitoring, regular inspection, maintenance, and status evaluation for recloser controllers, protection devices, and switchgear. Our professional team ensures long-term safety, extends equipment life, and reduces costs for renewable energy developers.

Contact us for customized PV grid-tied protection solutions in the Latin American market!

Deployed Equipment

  • Overhead Line Protection Switch Intelligent Controller
    Description RWK-LCoverhead line protection switch intelligent controller is medium voltage overhead line grid monitoring unit, it can be equipped with RCW(RVB) type vacuum circuit breaker for achieve of automatic monitoring, fault analysis and event records. Its given to us a safety power grid for cutting line fault and automatic recovery operation and power automation. RWK-LCseries is suitable for up to 35kV outdoor switchgear using, include: vacuum circuit breakers, oil circuit breakers and
  • Line Sectionalizing Load Break Switch Controller
    DescriptionRWK-381 line sectionalizing load break switch controller is a kind of switch which must cooperatewith superior switch. It can’t cut off the fault current, it only trip when the line is low-voltage or no-current. RWK-381 line sectionalizing load break switch controller adopts IT operation mode. When a fault happed, the controller will record the fault times. If the times come to the setting value, the controller will trip after the line is low-voltage or no-current. The controlling box
  • RWK-35 Recloser Controller | ANSI C37.60 Protection & DNP3.0
    RWK-35 is an intelligent medium voltage controller designed for overhead line grid monitoring and protection. It pairs with CW(VB) type vacuum circuit breakers to deliver automatic monitoring, fault analysis, and event recording.This unit provides safe line switching of faults and automatic power recovery, significantly reducing outage duration and improving SAIDI/SAIFI metrics. Suitable for up to 35kV outdoor switchgear including vacuum, oil, and gas circuit breakers, the RWK-35 integrates line

Related Solutions

  • Distribution automation systems solutions
    What are the difficulties in overhead line operation and maintenance?Difficulty one:Overhead lines of distribution network have wide coverage,complicatedterrain,many radiation branches and distributed power supply,resultingin "many line faults and difficulty in fault troubleshooting".Difficulty Two:Manual troubleshooting is time-consuming and laborious.Meanwhile,therunning current,voltage and switching state of the line cannot be graspedin real time,because of the lack of intelligent technical m
  • Remote OM Technical Solution for South Africa Distribution Lines - RWZ-1000 Cloud-Based Monitoring
    Technical Framework for Digitally Reimagining Power Grid OM in South AfricaShifting from "post-fault repair" to "predictive maintenance," reshaping the operation and maintenance processes of the distribution network through digital means.Applications: Unmanned substations, cross-regional long-distance transmission lines, and high-risk operational zones.Product Portfolio: RWZ-1000 intelligent monitoring system and RW8000 cloud management platform.Standards: IEC 60870-5-104, IEEE 1547, and NRS 048
  • Recloser controller Intelligent insulation and dehumidification upgrade solution
    I.Background of the Proposal1. Countries or regions such as Indonesia, Malaysia, Singapore, the Philippines, Thailand, Vietnam, southern India, Bangladesh, Sri Lanka, Central America, Caribbean countries, coastal areas of Brazil, Colombia, and equatorial coasts of Africa are prone to the following hazards during long-term operation of controllers due to high temperatures, humidity, and salt spray: Internal condensation, circuit board moisture and short circuit Terminal oxidation and poor con
  • Frequent malfunctions and failures to trip in rural grid recloser controllers? A radical reliability solution achieves zero faults year-round.
    Technical Solution: Upgrading Recloser Controllers to Meet New Energy Integration and Grid Automation RequirementsAs renewable energy sources (such as solar and wind power) become increasingly prevalent, older recloser controllers—with their simplistic functions—are failing to meet the demands of modern power grids. This often leads to frequent malfunctions and power supply instability. Based on real-world applications, we have developed this comprehensive solution to resolve these adaptation ch
  • Recloser Controllers Communication Upgrade: Enhanced Protocol Compatibility and Stability for Faster Grid
    As distribution grid automation matures, recloser controllers must "communicate" seamlessly with master stations, FTU terminals, and ring main units (RMUs) to quickly isolate faults and restore power automatically. However, many legacy controllers suffer from "communication barriers" or "unstable connections," hindering grid automation. Based on a real-world county-level grid case, we have developed this communication upgrade solution to eliminate these hurdles.I. Pain Points: Protocol Incompati
  • Adapting to Extreme Environments: 4D Customization for High Altitude, Cold, Salt Spray, and Pollution to Boost Recloser Controllers Reliability
    Most recloser controllers are installed outdoors, facing year-round exposure to high altitudes, extreme cold, coastal salt spray, and industrial pollution. However, many current devices use a "one-size-fits-all" standard design without optimization for these harsh conditions, leading to frequent failures and premature breakdowns. Based on a real-world high-altitude case, we have developed this specialized solution to solve the "environmental maladaptation" of equipment in extreme conditions.I. P
  • Smart O&M for Recloser Controllers: Reducing Troubleshooting Time from 6 Hours to 30 Minutes
    Many recloser controllers currently in operation suffer from low intelligence; they lack real-time status monitoring, diagnostic traceability, and often have cumbersome user interfaces. This makes troubleshooting slow and labor-intensive, driving up O&M costs. Based on a real-world urban distribution case, we have developed a specialized solution to resolve these operational bottlenecks.I. Pain Points: High Costs and Slow Response TimesCore Issues No Status Monitoring: Inability to track tem
  • Technical Solution: Enhancing Recloser Controllers Reliability for 10-35kV Mid-Voltage Grids
    The recloser controller serves as the "protective brain" of 10-35kV medium-voltage distribution networks. Its reliability directly determines whether a line trips unnecessarily, fails to trip when needed, or causes large-scale blackouts. Currently, many devices suffer from poor material quality and oversimplified designs, leading to frequent malfunctions (nuisance tripping) or failure to operate, which severely compromises power safety. Based on a real-world rural grid case, we present a special
  • Full-Lifecycle Management of Distribution Grid recloser controllers: A Five-Stage Synergistic Solution to Five Core Pain Points
    The recloser controller is the "chief steward" of 10-35kV medium-voltage distribution networks. Standardized management across every phase—from model selection and manufacturing to installation, daily O&M, and final decommissioning—directly determines whether the power supply remains stable and if the grid can achieve rapid self-healing.This solution focuses on the "lifespan" of the controller, providing simple, actionable, and cost-effective measures for each stage. It achieves efficient fu
  • Distribution Automation — The Evolution from Reactive Repair to Active Self-Healing Smart Grids
    1. Industry Challenge: The "Physical Blind Spots" of Traditional Distribution Networks1.1 The "Manual Search" Era of Fault LocationIn traditional distribution networks, when a 10kV feeder trips, maintenance crews must patrolkilometers of line pole-by-poleto visually locate the fault point. This outdated operational model directly results in three critical consequences:Degraded SAIDI Metrics: Average outage durations typically exceed 120 minutes.Wildfire Risk: High-impedance ground faults (e.g.,
Leave your contact information to receive the full technical white paper, equipment list, and energy efficiency report for this case. Request Reference Materials
Recent Success Reference
Send inquiry
+86
Click to upload file
Download
Experts Electrical is dedicated to serving the personnel in the global power industry.
Join Experts Electrical, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!
App Store
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.
Email
E-mail
Chat
Manager
WhatsApp
WhatsApp